Installation Information for Fenesta Windows
Home > Services > Installation

InstallationInstallation

Old civil practices with wooden windows require windows frames to be installed in the beginning or during the civil work. However, in the case of Fenesta, the complete window comes as one unit and is fitted after all civil work is over.

The correct stage for installation of Fenesta is just before the last coat of paint. The site should be clear of unnecessary material like cement, scaffolding to avoid damage to the windows.

Steps in the installation process

  • Site survey: the measurement of each aperture by experts. This information is used to make technical drawings of each window design using sophisticated CAD software.
  • These drawings are sent to the fabrication unit with instructions for manufacture.
  • The finished windows are dispatched to your site on the appointed date, ready for installation.

The installation process

  • The windows are fixed in each aperture with anchor fasteners
  • Gaps between the masonry and the frame are filled with high grade silicone and an acrylic sealant
  • Each window is tested and certified for operation
  • Each window is cleaned thoroughly
  • The debris is cleared and the site restored to its original state